CONSTRUCTION AND RRM
Crocodile Gorge Upgrade (N4-7 km 74.1 to km 90.05)
Project Details: Upgrading and Rehabilitation of Section 10
Commencement Date: March 2025
Expected Completion Date: February 2028
Progress of completion: 23%
Traffic Accommodation: Stop/Go closure to be implemented as required
Main Contractor: Raubex Construction
Schoemanskloof (N4-6Y km 2,7 to km 62)
Project Details: Upgrading and Rehabilitation of Schoemanskloof
Commencement Date: October 2024
Expected Completion Date: October 2027
Progress of completion: 29%
Traffic Accommodation: Shoulder lane closures; Stop/Go closures to be implemented during construction
Main Contractor: TauPele Construction
Hectorspruit to Lebombo Border post (N4-8X km 39 to km 70)
Project Details: Rehabilitation of the N4
Commencement Date: May 2025
Expected Completion Date: May 2027
Progress of completion: 15%
Traffic Accommodation: Lane closures; Stop/Go closures to be implemented during construction
Main Contractor: Roadspan/WBHO JV
Solomon Mahlangu Drive to Bronkhorspruit (N4-1 km 21 to km 25 and N4-2 km 0 to km 30)
Project Details: Rehabilitation of the N4
Commencement Date: October 2025
Expected Completion Date: September 2027
Progress of completion: 6%
Traffic Accommodation: Shoulder and Lane closures to be implemented during construction
Main Contractor: TauPele Construction
Van Dijksdrift Interchange to Wonderfontein (N4-4 km 9 to km 47 and N4-5 km 0 to km 10)
Project Details: Rehabilitation of the N4
Commencement Date: September 2025
Expected Completion Date: March 2027
Progress of completion: 8%
Traffic Accommodation: Shoulder and Lane closures to be implemented during construction
Main Contractor: Actophambili Construction
Ressano Garcia Border Post to Moamba Interchange (EN4-1 km 0 to km 41.29)
Project Details: Rehabilitation and the construction of a new passing lane of Section 16
Commencement Date: October 2024
Expected Completion Date: December 2027
Progress of completion: 20%
Traffic Accommodation: Stop/Go closures
Main Contractor: WBHO Projects Mozambique
Moamba I/C to Tchumene Interchange (EN4-2 km 0 to km 25)
Project Details: The mill and replace of N4 MDC section 17
Commencement Date: June 2025
Expected Completion Date: July 2025
Progress of completion: 10%
Traffic Accommodation: Daytime Stop/Go closures
Main Contractor: TC Projectos LDA